Queensland Price Quality Method Explained
Learn how Queensland’s Price Quality Method scores price and quality, the thresholds that trigger it, and the exact steps to submit a compliant tender.
What is the Queensland Price Quality Method?
The Queensland Price Quality Method (PQM) decides who wins a contract by balancing price against quality. It replaces the lowest‑price test that many private contracts still use. Queensland publishes a guide note that spells out the weighting and the scoring rules. The method sits inside the broader Commonwealth procurement philosophy that looks for value, not just the cheapest offer. It gives agencies a tool to reward better outcomes.
Because PQM scores two dimensions, you cannot rely on price alone. A strong quality score can lift a bid that is a little higher in cost. Conversely, a weak quality score will sink even the cheapest proposal.
How does the method score price and quality?
Each tender receives two separate scores.
- Price score: compares the quoted amount with the lowest compliant price.
- Quality score: measures how well the tender meets the technical, commercial and risk criteria set out in the tender documents.
The guide note then applies a predetermined weight to each score. The final composite score decides the winner. Typical weightings give quality a larger share than price, for example sixty percent quality and forty percent price. The exact split is printed in the tender's evaluation schedule. Follow that schedule exactly; any deviation can lead to disqualification.
Key point: A higher quality score can offset a higher price, as long as the weighted total remains the best.
Practical tip
If you can improve your quality narrative without raising cost, do it. The extra effort often pays for itself in a higher composite score.
What thresholds trigger the use of the Price Quality Method?
The Queensland guide note says the method is mandatory for contracts that exceed the state‑set monetary threshold. The threshold changes from time to time, so you should always confirm the current figure on the finance.gov.au site. In the Commonwealth arena, non‑corporate entities must open the market above A$80,000, and for construction projects the trigger rises to A$7.5 million. Those Commonwealth thresholds give a useful benchmark, but Queensland may have its own numbers.
Because thresholds shift, the safest practice is to check the latest Queensland procurement policy before you start writing your bid. A quick look at the portal can save you from re‑working a submission later.
Why the threshold matters
Below the threshold, a simple lowest‑price test may apply. Above it, the evaluator must run the full PQM calculation. Missing the threshold can invalidate your whole approach.
What documents must I prepare to meet the method's requirements?
First, you need an active Australian Business Number (ABN). Applying for an ABN through the Australian Business Register is free and mandatory for any government contract.
Second, you must supply all the technical and commercial information the tender asks for. That often includes a statement of work, risk management plans, and a Safe Work Method Statement (SWMS) that meets Queensland's work health and safety regulations.
Third, you should prepare a clear pricing schedule that isolates the cost elements the evaluator will compare. Finally, include a quality narrative that maps your capabilities directly to each evaluation criterion.
- Use the exact language from the tender's evaluation schedule.
- Reference past projects that match the required outcomes.
- Provide evidence of any sustainability or innovation claims.
Aligning your submission to the wording in the schedule makes scoring straightforward for the evaluator.
Document checklist
- ABN confirmation
- Technical proposal
- Commercial proposal
- Pricing schedule
- Quality narrative
- Compliance declarations
How does the Price Quality Method differ from a lowest‑price evaluation?
In a lowest‑price test, the contract goes to the bidder who offers the smallest amount, provided they meet the minimum technical requirements. The Price Quality Method adds a second dimension. Quality can include experience, innovation, sustainability measures, after‑sales service and risk mitigation. Those factors receive a score that can outweigh a modest price difference.
Because the method looks for value for money, it tends to attract bidders who can demonstrate stronger outcomes rather than just cheap labour. It also reduces the risk of selecting a supplier who cannot deliver the required standards. The extra focus on quality often leads to better project performance.
When a low price hurts
If you chase the cheapest price and ignore quality, your bid will likely score poorly on the quality side. The composite score will drop, and you may lose even if you are the lowest price.
Where can I find the official guide and related resources?
The Queensland Price Quality Method guide note is published on the Queensland government procurement portal. It explains the weighting, the scoring tables and the documentation you must submit. For Commonwealth contracts, the Commonwealth Procurement Rules reinforce the same value‑for‑money principle. Those rules state that non‑corporate Commonwealth entities must open the market above A$80,000, with a higher construction threshold.
If you are new to government tenders, start with AusTender, the Australian Government's procurement portal. It lists all Commonwealth opportunities and provides links to the relevant rulebooks. For Queensland‑specific tenders, use the state portal and search for the Price Quality Method tag.
Free search tools like TenderWin let you filter for Queensland contracts that use the Price Quality Method. While the basic search is free, the platform's advanced bid tools require an account.
Quick resource list
- Queensland procurement portal, guide note download
- AusTender, Commonwealth opportunities
- TenderWin, Queensland contract filter
Bottom line: Understand the weighting, meet the threshold, supply the required documents and align your narrative to the evaluation criteria. Follow those steps and the Price Quality Method becomes a clear path to winning Queensland government work.
Frequently asked questions
What does the Queensland Price Quality Method measure?+
It measures both price and quality using a weighted formula to find the best value for money.
When must I use the Price Quality Method in Queensland?+
It applies when the contract value exceeds the threshold set in the Queensland guide note.
Do I need an ABN to bid under this method?+
Yes. An active ABN is required for any government contract.
How is the weighting decided?+
The guide note specifies the split, often something like 60 % quality and 40 % price, but you must follow the published schedule.